Issue · Town spending
Westpark waterline developer reimbursement
Updating Authorization for Developer Reimbursement Agreement – Westpark is listed on the October 6, 2026 agenda as item 12.e.
Current status
In progress
Town Council, October 6, 2026: Resolution 2026-143. Approved, announced 7-0.
Spending
Amount: $410,332 · Vendor not stated · Funding source: No additional funding is needed. As approved by Resolution 2025-155, the reimbursement agreement and associated minimal land acquisition costs ($410,332) will be funded under the Townwide Waterline Improvements and Repairs project (#20505) which is an approved project in the Town’s Adopted Fiscal Year 2027-2032 Capital Improvements Program (CIP).
What it is
What Council was asked to do: Approve the proposed resolution, which modifies the reimbursement provisions in Resolution 2025-155.
Last updated Saturday, November 14, 2026, afternoon, America/New_York.