Item 12.d · Consent agenda
Chesapeake Bay TMDL Phase III Design Contract Awards
Chesapeake Bay TMDL Phase III Design Contract Awards is listed on the June 23, 2026 agenda as item 12.d.
Approved
Motion 2026-104. Resolution 2026-091. Approved, announced 7-0.
The purchase
Amount $1,113,008. Vendor Rummel, Klepper & Kahl. Funding No additional funding is needed. The recommended contract for the Chesapeake Bay TMDL Phase III CIP project with Rummel, Klepper, and Kahl is $1,113,008, which includes both design and contingency expenses. The Chesapeake Bay TMDL Phase III CIP project is an approved project in the Town’s Fiscal Year (FY) 2027-2032 CIP, with the life-to-date appropriation of $3,742,749 funded primarily through line of credit.
The record
RecordIssue page
Last updated Wednesday, November 11, 2026, afternoon, America/New_York.