Supplemental Appropriation and Contract Award for Stormwater Utility is listed on the July 28, 2026 agenda as item 12.f.
Current status
In progress
Town Council, July 28, 2026: Motion 2026-130. Resolution 2026-113. Approved, announced 5-0-1-1 (steinberg abstain, vice mayor cimino-johnson absent).
Spending
Amount: $248,600 · Vendor: WSP · Funding source: A supplemental appropriation is necessary as this cost was not included in the Fiscal Year 2027 Adopted Budget. The task order for the second and third phases of implementing a stormwater utility is $248,600. As a one-time use, reserves are the appropriate funding source, and the use of this reserve is consistent with the funding of stormwater operations in the Fiscal Year 2027 Adopted Budget.
What it is
What Council was asked to do: (1) Approve a supplemental appropriation in the amount of $248,600 from the Data Center Computer Equipment Tax Reserve. (2) Authorize the Town Manager to execute a task order with WSP USA Environment & Infrastructure, Inc. for the next phase of consultant assistance to develop and establish a stormwater utility.
Last updated Saturday, November 14, 2026, afternoon, America/New_York.