Issue · Town spending

Stormwater utility study

Supplemental Appropriation and Contract Award for Stormwater Utility is listed on the July 28, 2026 agenda as item 12.f.

Current status

In progress

Town Council, July 28, 2026: Motion 2026-130. Resolution 2026-113. Approved, announced 5-0-1-1 (steinberg abstain, vice mayor cimino-johnson absent).

Spending

Amount: $248,600 · Vendor: WSP · Funding source: A supplemental appropriation is necessary as this cost was not included in the Fiscal Year 2027 Adopted Budget. The task order for the second and third phases of implementing a stormwater utility is $248,600. As a one-time use, reserves are the appropriate funding source, and the use of this reserve is consistent with the funding of stormwater operations in the Fiscal Year 2027 Adopted Budget.

What it is

What Council was asked to do: (1) Approve a supplemental appropriation in the amount of $248,600 from the Data Center Computer Equipment Tax Reserve. (2) Authorize the Town Manager to execute a task order with WSP USA Environment & Infrastructure, Inc. for the next phase of consultant assistance to develop and establish a stormwater utility.

Sources: July 28, 2026 agenda packet (opens in new tab)

Last updated Saturday, November 14, 2026, afternoon, America/New_York.